You do not need answers to all of these. Every one you do have makes the estimate visit faster and the fixed scope tighter.
Before the estimate visit
- Rough drop count: desks, phones, printers, cameras, access points, displays
- A floor plan, even a leasing brochure PDF, with the furniture layout if it exists
- Where the equipment room or closet is today, and whether it can stay there
- Lease term and any landlord rules about ceiling access or after-hours work
- Which systems must stay live during the work, and your quiet windows
- Who owns IT: in-house, an MSP, or a vendor we should coordinate with
- Growth that is actually planned: headcount, a second suite, more cameras
The build-out sequence
For tenant improvements and new construction, this order keeps low voltage off the critical path.
- Design phase: closet location, pathways, and sleeve locations agreed with the GC
- After framing, before drywall: boxes mounted, cable pulled, rough-in photographed
- After ceiling grid, before tile: overhead runs, J hooks, and access point drops
- After drywall and paint: terminate, build and dress the rack, label everything
- Before occupancy: test and verify every port, with photos of the finished work in the closeout package
The reasoning behind the sequence is in the tenant improvement guide.